Will my Cabinet member need to rank my project for it to be prioritized?
Under the new governance process, Cabinet members will not have to rank every new request manually. Instead, each request must identify an Executive Sponsor (Cabinet member or AVP) and a dedicated business process owner from the outset. This ensures accountability at the right leadership level and boosts project success. Projects will be prioritized based on the scoring model. |
-
What happens if my project request is in the backlog?
Any projects yet to start or any new requests will be placed in a separate backlog until we have the capacity to take them on. Once resources become available, these requests will be scored and scheduled. This helps us avoid overcommitting our teams and compromising quality.  |
-
UITS is moving some projects to a “backlog†list. Will the information I submitted be deleted when the projects are moved?
All project data remains in our management system for future reference.  |
-
The new project submission process requires current process documentation that has been reviewed for efficiencies and updates be submitted with my request. What is a business process?
A business process is simply a step-by-step way of getting something done in your department or office. It’s the set of activities people follow to complete a task—from start to finish. For example, approving a student’s travel request, onboarding a new hire, or ordering lab supplies are all business processes.
Before we can help you with your request, we need to understand your current process clearly:
- Who does what?
- When do they do it?
- What decisions are made?
- What information is passed along?
Having a well-documented business process helps ensure:
- We're solving the right problem
- We're not automating an inefficient or outdated method
- Everyone involved understands and agrees on how things work (or should work)
- We can design an automation that truly improves the experience
|
-
What format does my business process documentation need to be in to submit it with my request?
You may submit a Word document or a PDF with the process documented. The documentation
can be written in narrative form or presented as a diagram.
When creating your business process, it may be helpful to think about what each step in your process accomplishes instead
of what you do physically. What would you need to do to accomplish your business objective if there was no technology available to complete your process. For example, if you submit a request to a manager for approval, we want to know that the request needs to be approved by a manager—not necessarily that you draft and send an email.
Consider the following questions as you work on the process document:
- What information is needed for the approval?
- Who has the authority to approve?
- What regulation or policy states the requirement for the approval and who can approve?
|
-
What are the responsibilities of the Executive Sponsor?
Executive Sponsors must meet the following criteria and are responsible for the following activities:
- Must be a Cabinet member or AVP
- Possesses budget authority and commits to financial support of the project
- Final Business Process decision-making authority
- Champion of project within University Leadership for governance and strategy discussions
and negotiations
- Participates in IT Steering Committee meetings though may not be involved in each project meeting
|
-
What are the responsibilities of a Project Sponsor?
-
The Project Sponsor must meet the following criteria and be responsible for the following
activities:
- Strategy Alignment: Define the business goals of the project and explain how the project goals align with
the strategic goals of the University.
- Resources: Commit specific business area/academic area project team members to the project and
ensure team members fulfill their commitments to the project.
- Continuity and Leadership: Remain engaged in the project for the entirety of the project; participate in all project meetings.
- Data Governance: Review and obtain data steward approval for use or collection of University Data related
to the project.
- Financial Resources: Request or provide support/approval for financial obligations for the project.
- Business Decision Making: Support timely business-oriented decision making and timely evaluation of business process improvements or changes.
- Business Process Conflict: Facilitate business process conflict discussions with other stakeholders.
- Change Management Champion: Propose, plan, and engage in organizational change management initiatives to ensure the success of the project; communicate and gain buy-in for the vision and goals of the project from organizational leaders and within the requesting team.
- Horizontal and Vertical Communication: Responsible for communication with the Executive Sponsor and other leaders within
the requesting department/division.
- Scope and Goals: Define the business objective boundaries of the project and co-approve the scope with
the technical team.
- Realization of Benefits: Collaborate with the Executive Sponsor to define the project goals and success metrics
(How will you know if the project accomplished its intended purpose?).
- Is this metric meaningful?
- Is it measurable?
- Where/how will the team obtain the data to measure the metric?
- Who is responsible for collecting the data and measuring the success of the project?
- How long will it take to see a response in the metric?
- Project Change Management: Evaluate project change requests for impact and acceptance (scope, budget, timing,
process owner/SME).
- Availability: Be accessible to the project manager, Executive Sponsor, and other project team members for updates.
|
|
-
What are the responsibilities of a Business Process Owner?
Business Process Owners must meet the following criteria and are responsible for the following activities:
-
- Full-time employee
- Knowledgeable of the business process related to the request and intersecting business processes
- Has appropriate authority to make decisions about business process changes
- If no authority to make business process changes, has the authority and access to
facilitate discussions with department leadership
- Process Design: Responsible for describing and explaining the current business process or processes related to the request including challenges, issues, time spent completing the process, common errors, number of people needed to complete the process, metrics used to evaluate the process, tools currently in use to complete the process, and identifying intersections with other processes
- Responsible for redesign of business process, as needed, to accommodate efficiency opportunities or adjustments needed for process optimization
or compliance requirements, and documenting expected impacts of proposed process or
technology changes
- Process Documentation: Create and maintain updated process documentation including process maps, standard
operating procedures, work instructions, support materials for the process(es), and
roles and responsibilities related to the process(es)
- Process Implementation: Responsible for coordinating with cross-functional teams with overlapping or tangential
processes, providing support to process participants, obtaining support from Executive
Sponsor and other leadership in related departments for process changes and adoption;
serves as point of contact for other business units for questions or discussion about
the current or new process, working with leadership and management to identify process
participants and assign roles and responsibilities to process participants
- Process Monitoring and Evaluation: Identify meaningful metrics to evaluate the effectiveness and efficiency of the process;
Identify data needed for effective measures; Collect and evaluate baseline data for
the current business process; collect and evaluate data after process changes (This
data will be used to evaluate future requests for technology enhancements); Identify
process deviations and bottlenecks
- Process Compliance: Responsible for researching and ensuring processes comply with all policies, guidelines,
regulations etc. from the University, USG, or other governing body.
- Training and Development: Ensure all stakeholders involved in the process have the necessary knowledge, skills, and abilities to complete the process
|
|
-
Will there be more changes to the IT Project Request process?
You can expect additional process updates over the coming months as we put formal IT governance in place. We will keep you informed through the Weekly Feed and will directly contact requesters whose projects move to the backlog. 
Our goal is to undertake as many projects as possible but also be realistic about the timelines and our ability to complete work as promised and without impacting other demands. We will also update this page with guidance on submitting new requests.
|
|